Auburn University Regional Airport in Alabama, USA, is getting its first air traffic control tower, and the most delicate job on site was setting the glazed controllers' cab on top of the shaft. ALL Crane Rental of Georgia, part of the ALL Family of Companies, did the lift with a six-axle Liebherr LTM 1400-6.1 all-terrain crane that had only joined the ALL fleet in June 2026. The general contractor is Stone Building Company. ALL has not given a date for the lift; the company described the job in late October 2026.
The load and the set-up
The cab, which ALL calls the observation deck, was fully built on the ground. It weighs about 42.6 tonnes (94,000 lb), is 10.4 m in diameter and 9.1 m tall. A steel cradle was placed underneath it. To keep the load off the cab structure itself, the slings ran down to the cradle through four openings in the roof and four in the floor. The supporting shaft, almost 30 m high, was already in place; the finished tower stands around 33 m.
| Item | Value |
|---|---|
| Load | approx. 42.6 t |
| Cab size | 10.4 m diameter, 9.1 m high |
| Radius | approx. 16.8 m |
| Main boom | approx. 55.2 m |
| Counterweight | 140 t |
| Also used | Y-guying, outriggers fully extended |
| Time on the hook | 5 hours |
The radius was short, about 16.8 m, but the cab is bulky, and only around 2 m separated it from the crane operator's cab. ALL planned the lift in advance in Liebherr's Crane Planner 2.0 software, which works with the crane's LICCON control system.
Once the cab was in position the crane kept holding it for five hours while an eight-strong ironworker crew fastened it to the tower. Only then was the cradle released.
What Y-guying does
A 55 m telescopic boom carrying a heavy load bends both downwards and sideways. Y-guying, as Liebherr calls it, adds two struts on the boom with tensioned ropes running from them to the boom head. Like the stays of a cable-stayed bridge, they take load off the boom and noticeably raise capacity on long boom lengths. The LTM 1400-6.1 is the smallest Liebherr crane offered with the system.
Why not a bigger crane
A crane in the 500 to 550 tonne class could also have done the job, but it would have needed its boom fitted on site, because machines of that size travel without it. That takes clear space, and there was not enough next to the tower. The LTM 1400-6.1 drives on public roads with its boom on board, the boom head resting on a separate dolly. It came from ALL's yard in Mobile, Alabama, and was ready to work without any boom assembly.
The crane
Liebherr launched the LTM 1400-6.1 in 2024 as the successor to the LTM 1350-6.1. It is rated at 450 tonnes at 3 m radius, with a telescopic boom of up to 70 m, lattice extensions of up to 80.5 m and 140 tonnes of total counterweight. At Conexpo 2026 in March, Liebherr handed the first unit in the United States to ALL Erection & Crane Rental.
The tower
The airport needs the tower because traffic has grown, driven largely by Auburn University's flight training programme. The project budget is 9 million dollars, 7.2 million of it allocated by the US Congress. Construction started in autumn 2025.
Source: ALL Crane