Centre of gravity & load distribution (beta)
Total mass and centre of gravity of a rigid load made of several items, a plan of the points, and the vertical forces at two points when two vertical forces can balance the load.
Beta: not for real calculations
Result
Beta: not for real calculations
The results refer to the load model entered and to static equilibrium of vertical forces. They do not replace checking the rigging arrangement, the strength of the attachment points and the lifting plan.
How it is calculated
The load is a rigid assembly of items whose mass and own centre of gravity are known. Gravity is taken as uniform, so the centre of gravity is the centre of mass. All items and points use one right-handed system: X along the load, Y across it (to the left on the plan), Z up; negative coordinates are allowed. Masses are converted to kilograms and coordinates to metres.
M = Σ m_iX_G = Σ(m_i × x_i) / M, Y_G = Σ(m_i × y_i) / MZ_G = Σ(m_i × z_i) / M — only if Z is entered for every included itemW = M × g₀ / 1000 kN, g₀ = 9.80665 m/s²; 1 tf = 9.80665 kN
A missing X or Y is an error, not zero. If Z is missing for even one included item, Z_G is not worked out: the known moments are not divided by the whole mass. Excluded items take no part in the sums and are listed in the report.
Two vertical forces
Two strictly vertical forces at points A and B and the weight act on the load; there are no other forces. With d = B − A in plan:
L = |d|, u = d / L, g = G − At = (g · u) / L — position of G along ABe = u_x × g_y − u_y × g_x — signed offset of G from the line AB, mR_A = W × (1 − t), R_B = W × t
Two vertical forces can balance the load only if G lies on the line AB (e = 0); the fact that G is between the points in X does not remove the moment across the line. If e is not zero, no distribution is given: the shares along AB are shown only as a diagnostic projection. If t < 0 or t > 1, one force is negative — a one-way suspension or support cannot provide it; the value is shown as calculated, not set to zero and not rescaled to 100 %. At t = 0 or t = 1 one point is unloaded — a boundary, not a confirmation of a two-point lift. The equilibrium ΣR = W and the moments about A in plan are checked on unrounded values.
Numerical accuracy
Masses and moments are summed with compensated (Neumaier) summation about a shifted origin, so large coordinates do not swallow small differences. Every intermediate value is checked to be finite; values outside the computable range give an error, not a result. Two tolerances are used, and both are numerical only: e and the distance of G from the ends of AB count as zero within 1e-9 of the layout size S = max(L, |G − A|, |G − B|) plus 1000 machine epsilons of the largest absolute coordinate; A and B are numerically indistinguishable if L is within 1000 epsilons of that coordinate. For a 4 m layout that is about 4 nanometres. This tolerance does not confirm how accurately the centre of gravity is known, and it is not a way to ignore a real offset. Close to a boundary more digits are shown with the note “close to the boundary”. No factor of 1.3 is applied: scaling all masses does not move the centre of gravity and does not remove uncertainty in the input data.
Help
- Enter the centre of gravity of each item itself — not its edge or the insertion point of a drawing. A geometric centre is right only where the mass is spread accordingly; do not assume it for an engine or a loaded frame.
- Enter the mass of the whole item. A row “4 × 100 kg” with the known centre of the group is one item of 400 kg; if the four pieces are in different places and the centre of the group is not known, enter them as separate rows.
- All items and points must use one origin, one scale and one orientation.
- A vertical force at a point is not the tension in an inclined sling: with inclined legs the horizontal components must balance as well, and that is not worked out here.
- The height of the centre of gravity matters for whether the load tips about the line AB; balanced vertical forces do not prove stability, especially when Z is not entered.
- Four points are not worked out: four vertical forces have only three equilibrium equations, so the result depends on stiffness, sling lengths and the rigging. W/4 or sharing by area is not used.
What this calculation does not cover
- four points, W/4 or sharing by area;
- inclined legs, sling tension, WLL, a factor of 1.3;
- stability and overturning of the load — the height of G alone does not mean stability;
- three points — the next stage of the method;
- strength of lifting points, slings, spreader beams and the load itself; liquids, loose material and moving parts.
The masses of several parts can be added up first in the combined load weight calculator, downloaded as CSV and loaded here. Item masses are taken as they are, quantity already included; X and Y have to be entered.
Further reading
- NASA Glenn — Center of Gravity — the basic principle (textbook physics, not a lifting plan guide).
- Crosby — Rigging Information: Center of Gravity and Sling Loading (PDF) — two-point vertical sharing.
- CERTEX Finland — Chains, technical information — why multi-leg slings do not share the load equally.
- CERTEX Denmark — Center of Gravity Calculator — an example of a similar tool; its results were not checked.