Guide

Heavy crawler cranes explained: lattice booms, derricks and superlift counterweight

From 300 to 3,000 tonnes, a heavy crawler crane lifts more not because of its boom but because of how much counterweight it carries and how far back.

5 min read · updated

Liebherr LR 11350 crawler crane

The lattice boom crawler is the workhorse of the heaviest lifts on land – wind farms, refineries, nuclear plants and bridges. Models in the class run from 300 to 3,000 tonnes, yet they follow the same basic pattern: a bigger crane lifts more mainly because it can hold more counterweight further back.

The main parts

Undercarriage

Two crawler tracks and a carbody that carries central ballast – 95 tonnes on the Liebherr LR 1750/2. A wide track gauge and large track area spread the weight, so the crane can travel with load and needs no outriggers.

Superstructure

Cab, winches, engine and main counterweight, which runs to hundreds of tonnes: 245 tonnes on the LR 1750/2, 340 on the LR 11350 and up to 750 on the LR 13000.

Lattice boom

Built up from sections on site, with a fixed jib or luffing jib added for reach and height.

Why counterweight decides everything

A crane is a lever. The load tries to tip it forward and the counterweight resists, with the resisting moment set by both the weight and its distance behind the slewing centre. Superstructure counterweight cannot simply get heavier or move further back: the superstructure has to slew. Heavy cranes therefore add a second, remote counterweight.

Derricks and superlift

A derrick is a short second lattice mast behind the main boom, mounted on the superstructure. Additional counterweight hangs from its tip, often called superlift ballast. It sits tens of metres behind the crane and slews with it, either suspended or on a ballast trailer.

LR 1750/2LR 11350LR 13000
Maximum capacity750 t1,350 t at 12 m3,000 t at 12 m
Maximum load moment–22,748 tm65,000 tm
Superstructure counterweight245 t340 t750 t
Central ballast95 t30 t150 t
Derrick boomup to 38.5 m42 m54 m
Derrick ballast400 t600 t1,500 t

Derrick ballast is one and a half to two times the main counterweight. On the LR 13000 its radius can be varied steplessly from 20 to 30 metres, and a self-propelled modular trailer can replace the suspended ballast.

Note where the maximum ratings apply: 12 metres radius, not the 2 to 3 metres quoted for mobile cranes. Thousand-tonne loads are never compact.

The derrick has a cost. The crane needs a large, prepared, unobstructed circle behind it – often the deciding constraint on a congested site.

Moving counterweight instead

Manitowoc took a different route with its Variable Position Counterweight (VPC). The counterweight travels along the superstructure and automatically moves back or forward according to load, boom length and radius, removing the need for carbody ballast and reducing total counterweight. The VPC-MAX attachment adds a fixed 30 metre (98.4 ft) beam to take the weight further back while keeping it off the ground. Manitowoc reports that a 31000 with the system lifted a 670 tonne tower at a refinery in Ulsan, South Korea, with just 15 metres of space available for the counterweight.

Booms for wind

As turbines grow, booms are being stiffened. Liebherr's SX system for the LR 1750/2 inserts two or three extra-wide lattice sections – 3.5 or 6 metres wide and 14 metres long – into the lower main boom for lateral rigidity, allowing hub heights of up to 166 metres. XCMG's 1,300 tonne XLC18000M handles turbines up to 10 MW at 142 metres on its standard 150 + 8 metre wind boom without superlift, and up to 15 MW on a 198 + 8 metre boom with it. Working without a derrick speeds moves between turbine positions.

Classes and examples

ClassExamplesTypical work
300 tLiebherr LR 1300.1 SX, Manitowoc MLC300bridges, industrial erection, wind farm assist crane
600–800 tLiebherr LR 1750/2, Sany SCC8000Awind, bridge spans, petrochemicals
1,000–1,350 tLiebherr LR 11350, XCMG XLC18000Mlarge turbines, reactors, columns
3,000 tLiebherr LR 13000nuclear plants, columns up to 1,500 t, shipbuilding

When a load is heavier than any available crane, cranes work in tandem. In Melbourne in 2026, two 800 tonne Sany SCC8000As jointly lifted an 864 tonne bridge span that neither could have handled alone.

Transport and erection

  • Component weights. No LR 11350 component exceeds 45 tonnes at 3.5 metres wide; the LR 13000's heaviest part is 70 tonnes, and the crane weighs around 3,500 tonnes in operation.
  • Time. The first LR 13000, at Mammoet, reportedly took 12 days to erect. Builders of 1,000 tonne wind cranes now claim two to three days for erection or dismantling.
  • Ground. Despite large track areas, the crane needs level, prepared ground; current models display ground pressure to the operator in real time.

What to compare

  1. Load moment and the chart for the configuration you need – with and without a derrick, a crane can be two different machines.
  2. Space behind the crane for derrick ballast, or the case for moving counterweight.
  3. Boom options: height and tip load for wind, mid-radius capacity for industry.
  4. Logistics: truckloads, heaviest component, erection time.
  5. Ground bearing pressure in the working configuration.

Our articles "Why a 150 tonne crane rarely lifts 150 tonnes" and "Choosing a crane by its carrier" cover load charts and crane types in more detail.

This article is for reference only. It does not replace the manufacturer's documentation or a lift plan.

More articles

All articles →