Guide

Communication on the lift: how crane operators, riggers and signal persons talk – and why it breaks down

Almost every crane professional has had a communication failure on a lift in the past three months. Who gives the signals, which methods are used, and what to do when contact is lost.

5 min read · updated

Potain MDT 269 tower crane

A crane can be in perfect condition and the load well inside the chart, yet the lift can still end in an accident – because the operator did not see that the rigger was still at the load, or heard "up" when "stop" was meant. Most of the time the operator moves the crane on instructions from the ground rather than on what he can see. That makes communication as much a part of crane safety as a brake or a load moment limiter.

This article is for general reference. Signalling procedures, signal person qualification and communication requirements are set by national rules and the lift plan.

What the research found

In September 2026 the US National Safety Council (NSC) and the NCCCO Foundation, the research arm of the US crane operator certification body, published a report on rigging and signalling in crane work. It is based on a March 2026 survey of 376 crane professionals – 71 per cent of them operators – along with expert interviews and a literature review.

  • 98 per cent had run into communication problems on lifts at least sometimes in the previous 90 days.
  • Nearly half (47 per cent) said such problems at least sometimes forced a lift to stop.
  • 52 per cent described planning for rigging and signalling as rushed, inconsistent or missing.

The causes most often cited (respondents could choose several):

CauseShare of respondents
weather64 %
noise63 %
no line of sight61 %
inconsistent signals59 %
poorly trained signal person57 %
language barriers55 %
no designated signal person46 %

On unsafe rigging, people and organisation came up more often than equipment: gaps in riggers' knowledge, distraction, deadline pressure and weak supervision. Using US labour statistics, the report counts 405 work deaths between 2015 and 2024 in which a crane was the main or a contributing cause. Crane operators made up 29 per cent; most of the rest were people working at or under the load.

Who signals to whom

The operator runs the crane and is responsible for keeping within its limits – but often cannot see the load, which may be behind a building, in an excavation or on the far side of a roof.

The rigger chooses the slings, attaches the load, makes sure the hook is over the centre of gravity and moves clear before the lift.

The signal person is the operator's eyes, watching the load and its path and passing on instructions. On small jobs the rigger signals; on complex ones a separate signal person is appointed, sometimes two – one at the pick and one at the set-down – handing the load over between them.

The rule repeated in every set of industry standards: only one person gives the operator instructions at any time. The one exception is stop. Anyone who sees danger may signal stop, and the operator must obey.

How instructions are passed

### Hand signals

Hand signals are the main method when the operator can see the signal person. The set of gestures varies from country to country, although the main commands look similar. The international standard ISO 16715 describes a common set of crane hand signals, but on site the set required by national rules and the lift plan applies.

Their weakness is visibility: they cannot be seen in darkness, fog, behind obstacles or at long range. In the survey, lack of line of sight was the third most common cause of problems.

### Radio

On tall or spread-out sites, blind lifts and jobs with several cranes close together, radio is used. What makes it reliable:

  • a dedicated channel for each crane with no other traffic;
  • call signs, so every instruction starts by naming the crane;
  • continuous talk while the load is moving, so that silence itself means stop;
  • a radio check before work starts, with a fallback – hand signals or spare radios.

Its weaknesses are interference, flat batteries, noise and crews who speak different languages – all near the top of the table above.

### Cameras and sensors

Cameras at the boom tip or on a tower crane trolley, all-round view systems and sensors that detect people near the crane help the operator, but do not replace the signal person. They show the load; they do not tell the operator whether the people below are ready.

When contact is lost

The rule is simple: no communication, no movement. The operator stops and waits until contact is restored – no "just a little further". A signal person who loses sight of the load signals stop and moves to where he can see it.

To avoid getting there, plan communication as carefully as the lift itself:

  1. The lift plan names the signal person, where he stands, how instructions are given (hand signals or radio) and what happens if contact is lost.
  2. A pre-lift briefing for everyone involved, in one language. With a multilingual crew, agree the set of commands and check that everyone reads them the same way.
  3. A trained signal person, not whoever happens to be free. In the survey, 57 per cent named poor signal person training as a cause of problems.
  4. Record lifts stopped for communication reasons instead of brushing them aside – they will recur unless the cause is dealt with. The industry is moving towards shared records: ESTA will pilot incident data sharing from January 2027.

In short

Communication on a lift is part of crane safety, not a formality. One person gives instructions, anyone can call stop, and without communication nothing moves. Most failures come not from equipment but from noise, weather, poor visibility, lack of training and haste – which means they can be planned for.